Will few users allowed to use classic budget if the budget is not migrated
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
We are enabling the sn_invst_pln.enable_budget_allocation_v2 = true property to make use of budget functionality in SPW and Project workspace, we will be migrating some of the demands and projects to new data model. We would like to know if the records which are not migrated will be used as it is for certain duration.
we understand that those records which are not migrated, budget related information will not be visible in workspace but we would like to understand if the demands and projects which are not migrated can be used as it is in classic UI for budgeting purpose.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
2 weeks ago
Hi @ranjanak Yes. Unmigrated records will continue to support the classic UI for adding and viewing budget.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
2 weeks ago
Hi Vinay,
Thanks for your reply, we are looking for the same functionality for new records as well. Some of users belong to different region still want to use the classic UI even though the property is enabled.
