Do you guys have any sample risk assessment questions that you don;'t mind using. Ones that are not out of the box. Trying to get an idea of what others are using or if anyone has heard of a best practice set of questions. I am talking about Change risks
Thanks
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎04-06-2017 10:50 AM
I personally do not see value in risk assessment questions due to selection bias. In other words, I'm guessing that there is a bias toward low risk changes.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎04-06-2017 11:16 AM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎06-15-2017 04:16 PM
We are actually working on implementing the Risk Assessment and Risk Calculator this summer. We do have a set of Risk questions we are going to be using:
- Does this Change have the potential to affect a Critical Business Service?
- How complex are the implementation steps?
- Has the Change been tested?
- How many workgroups are required to implement the Change?
- What is the past experience of implementing similar Changes?
- How long will it take to verify the Change was completed successfully?
We have multiple choice responses and are currently piloting a spreadsheet for every Change that requires CAB. So far the response is good.