Change Risk Assessment is not setting impact
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-09-2025 09:52 AM
Hello,
I am trying to set Change Request Impact field from Risk Conditions but is not working. I simply want if Risk is High, Impact is High and so on to low. Any assistance is appreciated.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-09-2025 10:00 AM
Hi @purdue
I think you're mistaken. The risk and impact are ultimately determined by the combination of risk conditions and risk assessments. You can't just pass the threshold and update the impact.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-09-2025 10:37 AM
Hello,
Thanks for the response. Then how can I set the impact?
Chad
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-09-2025 10:40 AM
As I said, mate, based on the risk calculation, the impact will be set. So, the risk will be calculated based on the Risk Assessment questions + risk conditions, and then, as per the risk conditions, the impact will be set. Please try this in PDI without making any changes.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-09-2025 11:01 AM
Hello,
Can you please provide an example of the risk conditions to set impact if Risk Assessment is being used. I am not getting what needs to be done.
Thanks,