'Do the following in parallel' action in Flow Designer is not executing in order
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-21-2025 12:46 AM
Hello All,
I want 9 tasks to be created in parallel through Flow Designer for a catalog item. It is working but the issue is it is not following an order. It triggers Task2 first instead of Task1.
I want to trigger Task1 > Task2>Task 3 and so on. How to achieve this?
Thanks in advance!
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-21-2025 12:50 AM
Hi @User205031 ,
If you want them to be created on a row instead of random order, you should put them one after the other whiteout the wait condition. By doing this, they should be created in the right order.
If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.
Best regards
Anders
Rising star 2024
MVP 2025
linkedIn: https://www.linkedin.com/in/andersskovbjerg/
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-21-2025 12:56 AM
Don't use do the following in parallel.
Use the approach shared by @AndersBGS , create them one after the other and don't use Wait checkbox for task completion.
If my response helped please mark it correct and close the thread so that it benefits future readers.
Ankur
✨ Certified Technical Architect || ✨ 9x ServiceNow MVP || ✨ ServiceNow Community Leader
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
Hope you are doing good.
Did my reply answer your question?
💡 If my response helped, please mark it as correct ✅ and close the thread 🔒— this helps future readers find the solution faster! 🙏
Ankur
✨ Certified Technical Architect || ✨ 9x ServiceNow MVP || ✨ ServiceNow Community Leader