Hi All,
Can you please help me with the below answer ?
Which of the following statements is true of a Risk Response task?
A. Only one Risk Response task can be related to a Risk at a time
B. Only users with the risk_manager role or higher can be assigned to a Risk Response task
C. The risk admin role is required to assign the Risk Response task
D. The Risk Response task is automatically progressed through the states using a workflow
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-03-2024 10:56 PM
Hi @SandeepKSingh
Correct answer is :-
D. The Risk Response task is automatically progressed through the states using a workflow
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-03-2024 10:56 PM
Hi @SandeepKSingh
Correct answer is :-
D. The Risk Response task is automatically progressed through the states using a workflow