How to configure two different Change tasks form

DevtoSME
Giga Guru

I have two different types of change task. One for verifier and implementers. I need to put the additional implementers field on the implementation plan and the additional verifiers on the review task.

How do i add each field to their respective tasks with out them showing up on the change task form together.

 

 

2 REPLIES 2

brianlan25
Kilo Patron

You could use the type field (screenshot below) on the change task. Setting it to implementation for one task and testing for the verification task. Then use a UI Policy to make the fields visible basked on the type field.

BrianLancaster_0-1715212876292.png

 

Hi Brian, 

 

so i went to the change task for the implementation and used the uI policy to specify if the task as for implementation but in the UI actions i do not see the new custom field i created called "additional implementor"