Hi All,
Can anyone let me know how to reopen an existing Closed Problem Record in SNOW.
Actually I dont see any option on Problem Record.
Thanks,
SNOW@Das
Labels:
2 REPLIES 2
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-10-2018 01:50 AM
Hi
Set the problem state from closed back to in progress. This will re-open the problem
regards

Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-10-2018 01:53 AM
Hi,
If you reopen the problem please check its related records as well. Like tasks, changes and incidents if you have some relations with them.
In some cases we have incident attached to problem and in return changes.