Hello All,
Is there a way how to exclude a weekends from a lead time? Currently leadtimes are set like this: 2,3,5 and 9 days
unfortunately if change is create on Friday lead time end on Sunday. Is there a way how to exclude them?
Thank you
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
09-04-2023 01:19 AM
Hi,
Please create a schedule which excludes the week end.
And then you can use the script in this community post to calculate the lead time using the schedule.
Regards,
Karthik Nagaramu
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
09-04-2023 01:35 AM
Hi @HubisCZ ,
If you are measuring the lead time through SLA, you can create a schedule to only include weekdays and by that exclude weekends. You can read further in this knowledge article: https://support.servicenow.com/kb?id=kb_article_view&sysparm_article=KB0547302
If my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.
best regards
Anders
If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.
Best regards
Anders