Hi,
Can we create MTTR report on Change Request table? If yes, could you please tell me how we can achieve it.
Thanks in Advance!
Thanks,
Bhavani.
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-19-2023 01:05 AM
Hi @Bhavani13 ,
In general on a change request you have the created date/time and resolved date/time. due to this, you can create a "function field" to calculate the MTTR:
Created date/time and closed date/time
Create function field:
Change request MTTR:
Add the new column to the table:
Press "run":
If my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.
Best regards
Anders
If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.
Best regards
Anders
Rising star 2024
MVP 2025
linkedIn: https://www.linkedin.com/in/andersskovbjerg/

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-19-2023 01:03 AM
HI @Bhavani13 ,
Unfortunately No!!
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-19-2023 01:05 AM
Hi @Bhavani13 ,
In general on a change request you have the created date/time and resolved date/time. due to this, you can create a "function field" to calculate the MTTR:
Created date/time and closed date/time
Create function field:
Change request MTTR:
Add the new column to the table:
Press "run":
If my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.
Best regards
Anders
If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.
Best regards
Anders
Rising star 2024
MVP 2025
linkedIn: https://www.linkedin.com/in/andersskovbjerg/
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-19-2023 01:12 AM
Hi @Bhavani13
MTTR is mainly used for Incident not for change. For the change, you can create or use report to see how much time a change take from New - Assess - Auth - Schedule etc.
For this please check the metrics table.
If my response proves useful, please indicate its helpfulness by selecting " Accept as Solution" and " Helpful." This action benefits both the community and me.
Regards
Dr. Atul G. - Learn N Grow Together
ServiceNow Techno - Functional Trainer
LinkedIn: https://www.linkedin.com/in/dratulgrover
YouTube: https://www.youtube.com/@LearnNGrowTogetherwithAtulG
Topmate: https://topmate.io/atul_grover_lng [ Connect for 1-1 Session]
****************************************************************************************************************