Set Hours as the default unit instead of FTEs in the resource menagement

Juan Foga_a
Tera Contributor

There is a way to set a the default unit in the resource management workspace as Hours instead of FTE, for everyone?

2 REPLIES 2

Tanushree Maiti
Tera Patron

Hi @Juan Foga_a 

 

Refer KB: KB2746371 How to make hours default instead of FTE when redirecting from Project Workspace to Resour... 

 

Resolution

When the user navigates from the project workspace to the resource management workspace, the resource management workspace uses the effort type from the project workspace's allocation heatmap. 

So, it is recommended to select as hours view in the project workspace so that when you navigate to resource management workspace, it will also open in Hours view

 

 

Juan Foga_a
Tera Contributor

There is a way to make this default for everyone?