Hi Team,
Is there any way i can configure the requested item SLA as per the task sla defined. for example i have a catalog item with 3 tasks and every task has 2 hour resolution sla configured. My requirement is the requested item SLA should be calculated (2+2+2) and it should also calculate the elapsed time as per the sub task.
- 1,420 Views
1 REPLY 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎09-03-2020 11:41 PM
Hi,
I assume you have a workflow (on sc_req_item table) set up with the three tasks - each with a schedule duration of 2 hours?
In the workflow properties 'Schedule' tab - setting the Expected time to be 6 hours should set the RITM SLA for you.