Why is resource plan using default Labor Rate of \$50 (even though I have created a Labor Rate Card & assigned a different rate to the user)?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-07-2016 12:04 PM
I created Labor Rate Cards & put all the IT resources into 1 of the Labor Rate Cards. None of these Labor Rate Cards has a rate of $50.
When I go to create a test Resource Plan for my project & add 1 hour for a user that has a labor rate of $65, it shows a planned cost of $50.
It is obviously picking up the default labor rate of $50/hour.
I double check that the user is in 1 labor rate card (and only one). If I look at the Labor Rate Card for $65, that user shows.
What am I missing?
(New to SN)
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-08-2016 12:21 PM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-03-2016 10:53 AM
Hi
Where do I find the table above? I'm trying to create a Labor Rate Card for resources but I don't know how to find it in the Navigator. I'm using Helsinki and have the PPS plug-in installed.
Thanks!
Spring
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-23-2017 02:18 PM
Did you work this out? I am having the same problem -- 50 dollars is set somewhere.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-30-2017 05:08 PM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-06-2018 04:31 AM
The same problem, all my attempts to figure out how to use Labor Rate Cards have null results. Kindly ask you to share information if any.