Hi Poonam,



Business duration is calculated mostly by SLA it is associated with. SLA in turn may have schedules.


So for instance, P4 SLA was attached to ticket & was completed after 4 days then it would check for SLA working hours which may be 8 hours per day so Business duration would then be 32 hours. If we have holiday or in between which is well defined in schedule it would then be 24 hours.



You can refer below links for more details.


1. What is the definition of *business duration* ?? - ServiceNow Express Support


2. Business Duration vs. Duration



Thanks,


Jaspal Singh