Hi James,
Thankyou for reaching out, I ended up reaching out to NOWSupport, it turns out I was using a custom flow stage value that the business rule (that auto closes the parent) didn't recognise.
I was using the stage value 'Closed Complete' (closed_complete)
The business rule was looking for 'Completed' (complete) *please note the value needs to be complete not completed