Blackout Schedule in Change

JohnnySnow
Kilo Sage

Hi Team,

 

I was working on blackout schedules and was wondering if any one knows what the source "Change request" means in the below window. I assume we need CI for using black out schedules (correct me if wrong).

We don't use CIs in our environment, so is there a point of having blackout schedules? 

 

JohnnySnow_0-1729738124261.png

 

Thanks
Johnny

Please mark this response as correct or helpful if it assisted you with your question.
10 REPLIES 10

Vishal Jaswal
Giga Sage

Hello @JohnnySnow 

When you apply source as Change Request then with filter conditions you wll be able to target some active Change Requests however when you apply source as CI Class and then target cmdb_ci > Name or Sys_id then all active and non-active Change Requests are also targetted which means even if the Change for select CI in the blackout is closed you will still see this conflicts message.

VishalJaswal_0-1752680581274.png


Hope that helps!