Hi guys ,

I deactivated the OOTB change flow , how can reactivate it ?

1 ACCEPTED SOLUTION

yashkamde
Tera Sage

Hello @sriramsin ,

 

Navigate to the sys_hub_flow.list table view and attempt to activate the flow directly from there. If activation isn’t available through that interface, the alternative approach would be to clone the flow and then activate the cloned version instead.

 

If my response helped mark as helpful and accept the solution.

View solution in original post

7 REPLIES 7

yashkamde
Tera Sage

Hello @sriramsin ,

 

Navigate to the sys_hub_flow.list table view and attempt to activate the flow directly from there. If activation isn’t available through that interface, the alternative approach would be to clone the flow and then activate the cloned version instead.

 

If my response helped mark as helpful and accept the solution.

Ehab Pilloor
Giga Sage

Hi @sriramsin,

 

You can go to the Flow Designer, open the Flow and look for Activate button. Or you can make copy of it from options and Activate it if it requires some addition or removal.

 

Regards,

Ehab Pilloor

VaishnaviK3009
Kilo Sage

Hi @sriramsin !!

 

  • Go to Flow Designer → Flows

  • Search for the OOTB Change flow (for example: Change Request – Normal or similar)

  • Open the flow

  • Click Activate (top right)

  • Confirm activation

Mark this as Helpful if it clarifies the issue.