Change Task Date Validation
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎07-18-2024 07:38 AM
Hi Team I am trying to add validation for change task Planned Start and Planned End dates.
Planned start and planned end should be in between Change Planned Start and Change Planned end date and planned Start Date can not be after Planned end date, similarly Planned End date can not be before start.
I need a logic to validate this in a OnSubmit script, and it should work for all date and Time formats.
Thanks,
Apoorva
1 REPLY 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎07-18-2024 08:29 AM
Hi @Apoorva D ,
Please refer to below thread:
Please Mark My Response as Correct/Helpful based on Impact.
Thanks & Regards,
Sumanth meda