If we want to be able to create change tickets linked to a request does any one know if this should be done a the request, requested item, or task level? What would be most in line with ITIL? (I think the request is too high level so probably the requested item or the task...
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-22-2023 11:09 PM
Hi @rdriemeyer ,
According to what you're also stating, the correct thing would be requested item. Requests can contain multiple requested items which again can contain multiple tasks.
If my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.
best regards
Anders
If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.
Best regards
Anders
Rising star 2024
MVP 2025
linkedIn: https://www.linkedin.com/in/andersskovbjerg/
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-22-2023 11:09 PM
Hi @rdriemeyer ,
According to what you're also stating, the correct thing would be requested item. Requests can contain multiple requested items which again can contain multiple tasks.
If my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.
best regards
Anders
If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.
Best regards
Anders
Rising star 2024
MVP 2025
linkedIn: https://www.linkedin.com/in/andersskovbjerg/