ITSM Simulator - Configure Risk Conditions

Diane22
Tera Guru

Am trying to close off on the Configure sick conditions and it keeps failing for both Normal and Standard changes.

What I did:

- went to Change => risk conditions

-  disabled the Insufficient lead time

-  insert and stay on the Insufficient lead time

-  on the new form:  modified the name, made it active, set risk to high, adjusted to 7 days, and added a condition for normal.

-   repeated for standard changes with standard changes, but 3 days and moderate.

-   deleted all ... recreated new (no insert/stay), same outcome

-   tested with change .. and the risk is actually set correctly with the message stating the challenge with insufficient lead time, but the simulator task fails 😞

-   revalidated everything, but used a different path:

 -  opened a new normal change => edit risk conditions and rechecked everything

what am i doing wong?

moving onwards in the meantime, this one was confusing as it should have been simple and isn't 😞

 

 

1 ACCEPTED SOLUTION

doyin
Tera Expert

Make the third condition to be Model is Normal, and Model is Emergency for both Risk conditions respectively.

View solution in original post

14 REPLIES 14

Anmol Saxena
Tera Contributor

Hello @Diane22 Did you get the solution for it?

Hi, 

I used the following conditions (& deactivated "Change Risk Assessment")

Normal change task:

Model is Normal

Planned start date relative before 7 days from now

Planned start date is not empty

 

Standard change task

Model is Standard

Planned start date relative before 3 days from now

Planned start date is not empty

 

I hope this helps

 

sanjub
Tera Contributor

This method will work thanks.

Ben White
Tera Contributor

Thank you - this worked!