Dear Experts. 

 

I have a list of maintenance schedule and when I schedule a CI which is in the maintenance schedule it checks all the maintenance schedule inclusive the one that has the CI assigned . Is there a way to limit only the specific maintenance schedule to only the ones on which a CI is related?

 

Regards

Nilanjan

3 REPLIES 3

Nilanjan1
Mega Sage

There is a property in the change conflict that needs activation which will help to only run schedules for the affected CI's but is there a way in which I can say that it is within a scheduled window. 

Community Alums
Not applicable

Thank you @Community Alums  I was able to resolve the issue as you can see in the above comment that I have mentioned that there is a property if true... will not go through all the schedules but only will run through a singular schedule. What my ask is that if it is in Maintenance Schedule if it is in the maintenance schedule then can we see the conflict to be mentioned in the maintenance schedule... ?