stop sla on incident task when incident priority is not p1 or P2

mregragui_ext
Tera Contributor

Hello everyone can someone guide me through this need i want to stop sla on incident task when incident priority is not p1 or P2. ( i tried to dot walk the field incident in incident task but not working)

7 REPLIES 7

ersureshbe
Giga Sage
Giga Sage

Hello,

could you please confirm that you have established separate SLAs for incidents and Incident Tasks? If you have distinct response and resolution SLAs for Incident Tasks, you can specify them within the SLA Definition configuration. Kindly refer to the screenshot provided below.

 

ersureshbe_0-1729440910130.png

 

Regards,
Suresh.

@ersureshbe i didn't get your answer could please explain more ? Thanks in advance!

AndersBGS
Tera Patron
Tera Patron

Hi @mregragui_ext ,

 

Just dot-walk the incident table and state your condition:

AndersBGS_0-1729489167832.png

 

If my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.

 

best regards

Anders

 

If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.

Best regards
Anders

Rising star 2024
MVP 2025
linkedIn: https://www.linkedin.com/in/andersskovbjerg/

@AndersBGS  Hello i tried this one not working for me