What business rules auto-populate the Change Request's Actual work start and Actual work end?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎08-10-2023 03:29 AM
What business rules auto-populate the Change Request's Actual work start and Actual work end?
For some reason the Actual work start and Actual work end values are not entered. .
When you manually create a Change request, the value is entered there, but when the Change request is created from the request item, the value is not entered there.
What is it controlled by?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎08-10-2023 05:45 AM
Hi @ayano
Please check below 2 business rules on change table, related to actual start and actual end
Actual Start/End Date Validation=> This calculate duration if we have actual start and actual end value
Change Model: Set work start=> This set actual work start as per current date time
Please check and Mark Helpful and Correct if it help you.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎08-10-2023 08:04 PM
Thank you for the comment.
I checked 2 business rules.
However,
Actual Start/End Date Validation=> My change request records don't have actual start and actual end value.(because the fields are empty.)
Change Model: Set work start=> My change request records is not used change model. (because the model fields are empty.)
Is there any business rule to relate the actual start and actual end??
Thanks and Regards,