May we know why is there a duration for stages that do not have any numbers set on it?

Highlighted with yellow: (Completed / Complete Stages with 0 seconds)

find_real_file.png

This is the duration set in Flow Stages.

find_real_file.png

 

I observe that this is not the case in out-of-the-box.

In OOB, it has no duration for this.

 

Please advise what is the problem on this.

Thanks in advance.

6 REPLIES 6

Yousaf
Giga Sage

Hi John,

The duration fields show an expected duration on the stage formatter for records (particularly request items) that the workflow is running against.

Please refer to this link

Workflow stage duration question


Mark Correct or Helpful if it helps.


***Mark Correct or Helpful if it helps.***

Hello Yousaf,

Thank you for your response.

We can agree that it is informational.

However, how and why is that the in the example or OOB, the "Completed" stage has no duration or no details about 0 seconds in it?

find_real_file.png

 

Our "Completed" stage has "Completed - 0 seconds"

find_real_file.png

Do you know why?

Completed state doesn't require any duration because completed state is end of the flow and it has been marked after the task is completed so no actual duration is required for this


***Mark Correct or Helpful if it helps.***

I can see that the example is from old Workflow Process Engine.
Is this the same in new Flow Process Engine?

Our "Completed" stage is also at the end of the flow.
After the task, it will end and mark stage as completed.find_real_file.png

 