Visual Task Board made for Project Task table, Add Card,
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-23-2023 04:07 AM
Hello all.
I have Visual Task Board.
Type: Guided. Table: Pm_project_task.
Vertical Lane: State
Swimlane: (none)
Lets assume that I want to use this tool as a place to meet all my project team members.
They see their tasks, they mark their fulfillment and so on.
But there is a button "Add Card".
What for? If I add a project task, then it's gone somewhere. I can find it, but it seem that it is not attached to any project. Can I turn this button off? Or make it usable?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
06-02-2023 12:46 PM
Hi @not_convinced,
It appears that the 'Add Card' function does not suit project tasks very well as you're not able to link it to a parent task. I find the best place to add new tasks is using the planning view in the Project Workspace.
The 'Add Card' function does work well for example if you are using it to manage your Agile stories, or even Incidents.