- Post History
- Subscribe to RSS Feed
- Mark as New
- Mark as Read
- Bookmark
- Subscribe
- Printer Friendly Page
- Report Inappropriate Content
2 hours ago - edited 2 hours ago
Calculations and trigger points for every supported metric, with worked examples for the default metric in each health dimension.
How to read this reference
This article explains how each supported metric is calculated and when it adds a finding to an AI-generated project status report.
Default and supported metrics.
By default, one metric per health dimension is selected out of the box: Schedule Variance (Schedule), Cost Variance Issues (Cost), Resource Overallocation (Resource), and Open Risks (Scope). Other supported metrics are available in each dimension, and an administrator can change the selection if required. If an administrator selects any of those metrics, the calculations in this article describe how each one works.
Each default metric covers what it measures, the data it reads, how it is calculated, its trigger point, how findings are classified, and a worked example. The other supported metrics cover what they measure, how they are calculated, and their trigger point and classification.
The trigger point is the condition under which a metric adds a finding to the insights sent to the LLM. A finding is not a status. The LLM turns the findings into Red, Amber, or Green by applying the administrator's criteria.
Thresholds described here are the defaults used by the status report. All example numbers and criteria text are illustrative. Administrators write their own criteria, and the LLM makes the final decision.
1. Schedule
Schedule Variance (default)
What it measures. How far the project's end date has moved from its baseline end date.
Data read. The current end date, the actual end date (for completed projects), the most recent baseline end date, percent complete, and project state. If the project has no baseline, the metric compares against the originally planned end date.
How it is calculated. The variance in days depends on whether the project is finished. A positive number means late.
- Ongoing project: current planned end date minus baseline end date.
- Completed project: actual end date minus baseline end date.
The metric also expresses the variance as a percentage of the baseline duration.
Trigger point. The metric produces a finding when the end date differs from the baseline. Severity bands start at 7 days of delay, so a delay shorter than that falls below the lowest band. A project ahead of schedule is reported without a severity. In the status report the minimum threshold is set to zero, so every variance is passed to the LLM and the administrator's criteria decide whether it matters.
Classification.
|
Severity |
Days behind baseline |
|---|---|
|
Critical |
30 or more |
|
Moderate |
14 to 29 |
|
Minor |
7 to 13 |
Example administrator criteria. "Red: schedule variance is Critical, or more than 30% of tasks are overdue. Yellow: schedule variance is Moderate or Minor, or any milestone has been missed. Green: no variance or ahead of schedule, and all milestones on track."
Worked example. The baseline end date is 30 September, the current planned end date is 20 October, and the baseline duration is 120 days.
|
Stage |
Result |
|---|---|
|
Variance calculated |
20 days, or about 16.7% of the baseline duration |
|
Severity classified |
Moderate |
|
Finding sent to the LLM |
The project is expected to finish 20 days after its baseline end date (Moderate) |
|
LLM applies criteria |
Moderate variance matches the Yellow condition |
|
Project manager sees |
Schedule Health: Yellow |
Screenshot: Schedule Health status in the generated report, with the project's baseline and current end dates
2. Cost
Cost Variance Issues (default)
What it measures. The difference between actual and planned cost, by fiscal period and by expense type (CAPEX and OPEX).
Data read. Planned and actual cost for each fiscal period from the project's cost plan, plus the project's budget, work cost, and forecast cost fields. The fiscal periods are derived from the analysis date window. Results include a per-period breakdown of planned against actual by CAPEX or OPEX and by resource type.
How it is calculated. The variance is the actual cost compared with the planned cost, as a percentage of the planned cost.
Trigger point. In the status report, the minimum threshold is zero, so every variance, however small, produces a finding. The analysis covers all fiscal periods in the cost history, not only the latest one. The LLM then uses the administrator's criteria to decide whether a variance warrants Red, Amber, or Green.
Classification. The built-in severity guide is:
|
Severity |
Variance |
|---|---|
|
Critical |
25% or more |
|
Moderate |
15% to 24% |
|
Minor |
5% to 14% |
Example administrator criteria. "Red: cost variance of 25% or more in any fiscal period. Yellow: cost variance between 5% and 24%. Green: variance under 5% in all periods."
Worked example. One fiscal period has a planned cost of 100,000 and an actual cost of 118,000.
|
Stage |
Result |
|---|---|
|
Variance calculated |
(118,000 - 100,000) / 100,000 x 100 = 18% |
|
Severity classified |
Moderate |
|
Finding sent to the LLM |
Actual cost is 18% above plan for the period (Moderate) |
|
LLM applies criteria |
18% falls in the Yellow range |
|
Project manager sees |
Cost Health: Yellow |
[Screenshot: Cost Health status in the generated report, with the cost plan planned vs. actual]
Budget Variance Issues
What it measures. Whether actual plus planned spending exceeds the approved budget, so you can tell whether the project is over or under budget.
Data read. Actual cost, planned cost, and approved budget records, broken down by allocation type (CAPEX and OPEX, or custom cost types if the system is configured that way).
How it is calculated. The budget is summed across its records, then compared with actual plus planned spending.
Trigger point. In the status report there is no minimum variance, so every budget variance produces a finding. The status report looks at the current fiscal year only, rather than the whole project lifetime.
Classification. The built-in severity guide is the same as for Cost Variance Issues:
|
Severity |
Variance |
|---|---|
|
Critical |
25% or more |
|
Moderate |
15% to 24% |
|
Minor |
5% to 14% |
3. Resource
Resource Overallocation (default)
What it measures. Whether any resource is assigned more hours than their capacity allows. A resource at 150% is committed to one and a half times the hours they can work.
Data read. Resource assignments and each resource's capacity. Capacity comes from the resource's work schedule, minus exclusions. Only current and future periods are analyzed, and past periods are ignored. Allocation is broken down by week.
How it is calculated. For each resource in each period:
Trigger point. Any period where utilization is above 101% of capacity produces a finding. The finding reports the number of overallocated periods, the worst utilization percentage, and total allocated hours against capacity hours. This is the metric where a per-project override is most useful: an administrator can change the threshold for one project, for example to 120%, while other projects keep the default.
Example administrator criteria. "Red: any resource above 150% utilization, or overallocation in more than three periods. Yellow: any resource between 101% and 150%. Green: no overallocated resources."
Worked example. A resource has 52 hours allocated in a week with 40 hours of capacity.
|
Stage |
Result |
|---|---|
|
Utilization calculated |
52 / 40 x 100 = 130% |
|
Trigger point |
130% is above the 101% threshold, so the period is flagged |
|
Finding sent to the LLM |
One overallocated period, worst utilization 130%, 52 allocated hours against 40 capacity hours |
|
LLM applies criteria |
130% falls in the Yellow range, provided no other period meets the Red condition |
|
Project manager sees |
Resource Health: Yellow |
[Screenshot : Resource Health status in the generated report, with the overallocated resource]
4. Scope
High-Impact Change Requests (default)
What it measures. The number of open change requests with High impact. Scope health looks at all open Risks, Issues, Decisions, Actions, and Change Requests (RIDAC items), and change requests are the most direct indicator of scope change.
Data read. Change requests in the Pending, Open, or Work in Progress states. Closed change requests are excluded, and only those with High impact are counted. For each change request the LLM receives the number, description, priority, impact, category, approval status, assignee, due date, and work notes.
How it is calculated. There is no numeric formula. Open change requests with High impact are counted and listed individually, with their priority and category (resource, scope, schedule, or cost).
Trigger point. Every open change request with High impact is included, and this metric has no numeric threshold. A project with no open High-impact change requests produces no finding. Whether a given count matters is decided entirely by the administrator's criteria, which is why the criteria text for Scope should state counts explicitly.
Example administrator criteria. "Red: three or more open High-impact change requests, or any High-impact change request past its due date. Yellow: one or two open High-impact change requests. Green: no open High-impact change requests."
Worked example. A project has three open change requests with High impact. One of them is past its due date.
|
Stage |
Result |
|---|---|
|
Change requests counted |
3 open change requests with High impact |
|
Trigger point |
All three are open and High impact, so all are included |
|
Finding sent to the LLM |
The three change requests, with their priority, category, approval status, and due date |
|
LLM applies criteria |
Three open High-impact change requests, one past its due date, matches the Red condition |
|
Project manager sees |
Scope Health: Red |
[Screenshot: Scope Health status in the generated report, with the open change requests list]
5. Overall Health: combining the four dimensions
What it measures. The aggregate health of the project, derived from the four dimension statuses.
How it is determined. The LLM aggregates the Schedule, Cost, Resource, and Scope statuses. If the administrator has configured Overall Health criteria, the LLM uses them. If not, a built-in rule applies. Overall Health is the only section with a built-in fallback.
Trigger point. Overall Health is always generated, even when no criteria are configured.
|
Condition |
Overall Health |
|---|---|
|
Any dimension (Schedule, Cost, Resource, Scope) is Red |
Red |
|
Two or more dimensions are Yellow |
Yellow |
|
All other cases |
Green |
Worked example. Applying the built-in rule to the results from Sections 1 to 4:
|
Dimension |
Status |
|---|---|
|
Schedule |
Yellow |
|
Cost |
Yellow |
|
Resource |
Yellow |
|
Scope |
Red |
|
Overall Health |
Red (any dimension is Red) |
[Screenshot: Overall Health status alongside the four dimension statuses]