Alert level: critical. Resource assignment cannot be created for task with non-attribute resource...
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
We recently converted Resource Plans to Resource Assignments and now whenever we try to make a change to the converted Resource Assignments we get this error:
Alert level: critical. Resource assignment cannot be created for task with non-attribute resource plans
I understand it has to do with planning attributes. What do we need to setup to fix this? Thank you.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
Hi @StephenPMO ,
Check the following link related to attribute-based resource assignments:
Enable attribute-based resource assignments
Thanks
Anand
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
We followed these steps, but in step 4 the value was already True. Error still exists.
- Navigate to All > System Properties > All.
- Filter the name field to locate and open sn_pw.enable_resource_planning.
- Change the scope of the instance to Project Workspace.
- Clear the Value field and enter true.
- Select Update.