Calculate cost and benefit estimates on Project while creating project from demand

Amit Garg
Tera Contributor

When a project is created from demand the cost estimate fields (forecast_cost) in Project currency is not calculated. The fields in functional currency are populating fine but the project currency fields are not calculated. Cost plans needs to be modified manually in order to trigger the transaction post project is created.

Any suggestion on how can this be automated?

1 REPLY 1

Saiganeshraja
Kilo Sage
Kilo Sage

Estimate at completion(forecast_cost) -Sum of all actuals for past fiscal periods added to the planned cost for future fiscal periods.