Cost Plan's field "Total actual cost" doesnt update

Dario_C
Mega Sage

Hi everyone!

I have a problem with a field on the Cost Plan. The field 'Total Actual Cost (actual_cost_default_currency)' doesn't update with the total amount of the related Expense Line. The value remains at 0. I don't understand why. How does this field work?"

Dario_C_0-1699978054693.png

Thank you in advance

 
11 REPLIES 11

Dhiren Aghera
Tera Guru

Can you check if your expense line is in "Processed" state. Your actual cost does not reflect in the cost plan unless your expense line is in Processed state.

Hi @Dhiren Aghera  ! 

Yes, all my Expense Line are in Processed State. So is this the problem ? 

Its not a problem but OOTB functional behavior to update total costs only after expense lines are processed. Are you are experiencing the same for all cost plans or only these one? If only these one then try to create a new expense line against the same cost plan to trigger the update of total cost field. If its for all the cost plans then there is a defect that needs to be fixed.

Dear @Dhiren Aghera ,

sorry for my late answer,

Yes i'm experiencing fort all Cost Plans. So when i create a new Expense line, and at this one give an Asset, the Cost Plan Breakdowns and the field "Total Actual Costs" Doesnt update with a new value.