Creating resource assignment for a specific group produces multiple resource assignments
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
2 hours ago
Before switching to resource assignments (using Resource Plans), we were able to create a placeholder in the resource plan that represented an unnamed member of a specific group. This allowed the group’s resource manager to select an appropriate team member to fulfill the demand.
Now that we’re using resource assignments, creating an assignment for a group automatically generates multiple assignments—one for the group and one for every individual member of that group.
Have we lost the ability to request an unnamed group member and let the resource manager choose who should be assigned? See screenshot.