Financials are doubled when using Resource Assignments on Planning Tasks
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎01-27-2025 09:06 AM
I am using resource assignments within Project Workspace Planning. I am adding the resources to specific tasks using the resource assignment field. However, when I go to the Financials the cost amount is double.
The resource allocation daily list view is correct.
I have shown a sample of the resource assigned in the Planning resource assignment field. (No resource assignments at project level).
I have shown the Resource Daily data is correct in excel pic.
I have shown the Financials view in the app is doubled as well as the download of data from Financials view.
What is happening here??? No rate models, no specific rates assigned. Only the default rate of $50 is in play.
This is a show stopper. Please advise.