The Zurich release has arrived! Interested in new features and functionalities? Click here for more

Generate Labor Costs in Project Currency

Nat Hunter
Tera Contributor

We have done the necessary setup to generate labor costs for Resource Assignments but have found that the Cost Plans are generated in the "Functional Currency" rather than the "Project Currency".  Has anyone grappled with this issue before and if so, how did you solve for it?

Can anyone from ServiceNow advise if the generation of labor costs in project currency rather than functional currency is planned on the SPM roadmap and if so, when it is expected?

We need to decide if we need to customise as it makes no sense to plan labor costs on a project in the functional currency rather than the currency set for the specific project.  Thanks!

1 REPLY 1

Vinay3
ServiceNow Employee
ServiceNow Employee

Hi @Nat Hunter , labor cost plans based on resource assignments generate cost plans with both functional and project currency values populated out of the box. you will be able to see the values in 'project currency' either in the related lists in the classic experience or the details page of the new project workspace.

The new financials page does not yet support seeing the values in project currency. It is currently being planned to be released tentatively in Dec 2025 release.