How percent_complete be calculated in Test Management 2.0?

ParkHyunSun
Tera Expert

Hi there,

 

I've been testing some features of test management 2.0 in my PDI.

As I read NowLearning and docs, it seemed that Execution Suite and Test Sets are parent-child relationship as Test Sets and Tests are.

 

ParkHyunSun_0-1736751834414.png

 

Also, I could see percent_complete in both Test Execution Suite and Test Cycle.

In my knowledge, percent_complete in Test Execution Suite and Test Cycle should be automatically calculated with child ones, however, I couldn't see the changes.

And secondly, when I clicked short description in related list, all I could see was just assignment group, which didn't have any state field or something.

Is there anyone who can help me out with these questions?

 

Thank you.

1 REPLY 1

Mathias Jepsen
Tera Contributor

Hey ParkHyunSun,

 

For whatever reason, it doesn't work if you run the Tests from the Test version [sn_test_management_test_version] record, even though there's a Run button.

 

What you have to do instead is navigate to "Tests Assigned to me" in the Application Navigator, and then select the checkboxes of the ones you want to run a test on, and then hit the Run UI Action

MathiasJepsen_0-1743163899135.png

 

Then it should correctly populate the result column from your screenshot.