How to configure the Functional currency field?

diana felipe
Tera Contributor

Client Need: Financial reports must be submitted in MXN, even if the projects are in USD or other currencies.
I noticed that I need to change the Functional Currency field to MXN. My user is located in Mexico. However, I can't get the currency to change in the Functional Currency field.

4 REPLIES 4

Rafael Batistot
Kilo Patron

Hi @diana felipe 

 

May you try check the Company record

 

  • Navigate to the Company table (core_company)
  • Ensure the Default Functional Currency is set to MXN for the company your project belongs to.
If you found this response helpful, please mark it as Helpful. If it fully answered your question, consider marking it as Correct. Doing so helps other users find accurate and useful information more easily.

kaushal_snow
Mega Sage

Hi @diana felipe ,

 

The Functional Currency is tied to the system reference (or base) currency, driven by the instance locale and is essentially informational (read only) on the Cost Plan form, meaning you can’t change it per project to MXN just because a user is in Mexico; instead, you use the Entered Currency field (or the multi currency feature) to input amounts in a different currency, and the system converts them internally to the functional currency...

 

If you found my response helpful, please mark it as ‘Accept as Solution’ and ‘Helpful’. This helps other community members find the right answer more easily and supports the community.

 

Thanks and Regards,
Kaushal Kumar Jha - ServiceNow Consultant - Lets connect on Linkedin: https://www.linkedin.com/in/kaushalkrjha/

Hi kaushal_snow

Thank you very much for your response; I truly appreciate your support.

However, I still haven't been able to fully make the change. The solution I was able to achieve was to create a "Project Currency" view, for example. With the help of the Multicurrency plugin, I was able to visualize the amounts in the currency of the project or demand.

dianafelipe_0-1761263397170.png

 

 

dianafelipe_1-1761263422924.png

 



What I still haven't been able to do is change the financial baseline report. It continues to break down the information using the functional currency (USD), and it doesn't display the values in the project's currency.

 

dianafelipe_2-1761263512228.png

 

 

Hi @diana felipe ,

In this project workbench, you can click on configure column from the side panel and scroll down to the breakdown column and bring columns for project currency like cost in project currency / actual cost in project currency, etc. This project currency columns are the mane fields that store the converted value from the entered currency.