Imported Project Tasks defaulting to red status?

MBarrott
Mega Sage

Not sure what could be causing this but every imported project task I'm bringing in via an import set/transform map is having it's overall status default to red, even when the project itself is green. 

 

I figured it might be a conflict is planned/actual dates but I'm not seeing anything. If I manually remove all the tasks and create it by hand it comes in green which is the default. 

 

Project:

MBarrott_0-1734368850136.png

Project Tasks:

MBarrott_1-1734368900257.png

MBarrott_2-1734368981714.png

 

0 REPLIES 0