Is It Possible to Build a Personal Gantt Workspace in SPM?

Ryo14
Tera Contributor

[Background]

I am considering creating a custom Personal Gantt Workspace in SPM instead of using the standard Project Workspace.

The workspace would display tasks assigned to a selected user while preserving the following hierarchy:

 

Project
  |-Sub Project
        |-Project Task

 

When a user is selected, I would like to display only the Project Tasks assigned to that user in a Gantt chart while maintaining the Project → Sub Project → Project Task structure.

 

[Questions]

  1. If I create a new Workspace using UI Builder, is it possible to display a Gantt chart with the following hierarchy?
  2. Is it possible to filter the displayed data dynamically based on the selected user (for example, assigned_to = selected user)?
  3. Can the Workspace automatically use the currently logged-in user as the default filter value and initially display that user's personal Gantt chart?
  4. Has anyone implemented a similar Personal Gantt Workspace? If so, what architecture or approach would you recommend?

 

Any advice or examples would be appreciated. Thank you!

1 REPLY 1

Namita Mishra
ServiceNow Employee

Hi @Ryo14 ,

Thanks for raising this question with community.

 

I have created a short video to showcase that out of the box project WBS can be used for the same purpose - focus on the tasks assigned to particular user while maintaining the structure - just filter on the "Resource Assignees".  Point #3 is not available out of the box but otherwise I think this would suffice.

 

Hope this helps and if it does please mark the response as correct answer to help me and the community.

 

Have a Great Friday!

 

Thank You!

Namita Mishra