Item milestone not showing on SPW roadmap
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-02-2025 11:39 AM
I have 4 milestones in the project plan (see Task list), but only 3 of them are showing in the SPW roadmap (see Missing milestone on roadmap). If I add a new milestone to the project workspace it shows. Other projects are missing milestones as well. What needs to be done to get them to show?

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-15-2025 02:32 AM
Hi Stephen - try and remove the Milestone flag from that task, save the task and then re-add it and see if that did the trick. As far as I can see the dates and everything are aligned, plus the Sept one is showing on the roadmap.
I assume the integration with PPM is active and both project and project tasks feed through to SPW as expected.
Let me know how it goes.
Paula