I would like to ask, if there is a way to enable List calculation for lists viewed in the Project workspace, I did not figure out where/if this is possible.

The list calculation is enabled e.g. for the project, related list : Cost Plan.

The list calculation (E.g. Sum) is visible on the classic UI, but the same record when viewed in the Project workspace, does not show the calculation.

Could you please advise if this is available or not?

 

Thank you?

A.

4 REPLIES 4

Ankur Bawiskar
Tera Patron
Tera Patron

@Alpa82 

I don't think it works with Configurable workspace and it only works in classic UI.

If my response helped please mark it correct and close the thread so that it benefits future readers.

Regards,
Ankur
✨ Certified Technical Architect  ||  ✨ 9x ServiceNow MVP  ||  ✨ ServiceNow Community Leader

@Alpa82 

Thank you for marking my response as helpful.

If my response helped please mark it correct and close the thread so that it benefits future readers.

Regards,
Ankur
✨ Certified Technical Architect  ||  ✨ 9x ServiceNow MVP  ||  ✨ ServiceNow Community Leader

Alpa82
Tera Expert

@Ankur Bawiskar  thank you for the response. I would be also interested, if SN plans to enable this very useful feature also in the workspaces 
@Namita Mishra  would you know if there is a plan to have the Hierarchival view available also in the workspaces (project workspace)? 
Thank you

@Alpa82 

I believe I have answered your question and you can proceed to mark my response as correct.