Migrating from Agile 2.0 to Enterprise Agile Planning (EAP) in ServiceNow to aimed at aligning Agile execution with enterprise-level planning and delivery.

1 ACCEPTED SOLUTION

Scott Townsend1
ServiceNow Employee
ServiceNow Employee

Hi KazeemR,

Happy to discuss options.  We actually use the same story table (rm_story) in both Agile Dev 2.0 and EAP so migration of stories is more just assigning them to the appropriate EAP Team.  

Let us know if you have any questions.

Thanks,

Scott 

 

View solution in original post

5 REPLIES 5

Mark Manders
Mega Patron

What's your question? Or is it just a statement of what you are doing?


Please mark any helpful or correct solutions as such. That helps others find their solutions.
Mark

Scott Townsend1
ServiceNow Employee
ServiceNow Employee

Hi KazeemR,

Happy to discuss options.  We actually use the same story table (rm_story) in both Agile Dev 2.0 and EAP so migration of stories is more just assigning them to the appropriate EAP Team.  

Let us know if you have any questions.

Thanks,

Scott 

 

KazeemR
Tera Contributor

Any process of migrating the agile sprint to EAP sprint?

 

Hi KazeemR,

 

Unfortunately, we don't have a way to migrate agile sprints to EAP.  Part of the challenge is that EAP is a bit more restrictive in terms of sprint calendars.  Specifically, within Agile Dev, teams can have unique calendars while in EAP we require teams that are planning together to share a calendar. 

 

In terms of moving from Agile Dev to EAP, the thought (which may not always be perfect) was that teams would pick a point in time and start using EAP (without migrating sprints).  

 

I hope that helps (although maybe not ideal for every scenario) - and happy to discuss further.

Scott