Not creating expense lines for project when the time card is approved.

arunkumarju
Tera Contributor

Not creating expense lines for projects when the time card is approved and the expense lines are creating only for project tasks. 
Checked the system property 'glide.cost_mgmt.process_task_top_task' and the value is true.

3 REPLIES 3

PaulaaO
Mega Sage

Against what is the time card recorded? Project or Project task? Can you share a screen shot of the Time Card, Expense Line and Project preferences?

arunkumarju
Tera Contributor

Hello PaulaaO,
Below are the details:
 Against what is the time card recorded - Project Task
Attached the screen shot of the Time Card, Expense Line and Project preferences.

arunkumarju_4-1764925215789.pngarunkumarju_5-1764925224807.pngarunkumarju_6-1764925231597.png

 

 

Thank you for sharing these. From the screen shots it looks like OOTB behaviour - expense lines get generated based on time cards which are against project tasks. You can validate by recording time cards against the projects and approving these, the expense lines will be then against the project. Unless I am missing something...