OOB consolidated view for resource allocations and PTO in SPM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Tuesday
Hi everyone, I am looking for some guidance on the best OOB way to achieve a consolidated resource view in ServiceNow SPM Resource Management.
Currently, we are creating PTO/Time Off through My Calendar. I configured the com.snc.resource_management.exclude_events_from_schedule property, and PTO is now correctly deducted from the resource’s available capacity.
The business requirement, however, is to have one single view where the team can see the complete picture of a resource’s time, including:
Project/task allocations
Resource plans/allocations
PTO/Time Off
Potentially other non-working/busy time
For example, the client would like to be able to look at a resource and see something similar to:
Resource A
Project A → 20 hours
Project B → 12 hours
PTO → 8 hours
We initially looked at the Allocation Workbench, but PTO created through My Calendar does not appear there. However, the requirement is not specifically to show PTO in Allocation Workbench; they simply want all of this information available in a single consolidated view.
Is there an OOB Resource Management calendar, workspace, dashboard, or other view that provides this consolidated visibility of allocations and PTO/time off?
If not, what would be the recommended approach in SPM to provide this visibility while continuing to use the standard PTO/calendar functionality and capacity calculations?
Thanks!
- Labels:
-
Resource Management
