Join the #BuildWithBuildAgent Challenge! Get recognized, earn exclusive swag, and inspire the ServiceNow Community with what you can build using Build Agent.  Join the Challenge.

Percent Complete in Planning Console not updating

stephenb
Tera Contributor

I have a project (Utah version) while working in the Planning Console the % completed field does not update unless/until i delete or add a task -- refreshing the screen does not work either.  Not sure if this a known bug or maybe an anomaly in my project.

 

Any assistance would be appreciated. 

1 REPLY 1

danielmartins
Tera Contributor

You need to create the rollup for planned task fields. Have a look here on how to do it: Configure rollup for planned task fields