Project Actuals and Resource Management Workspace

Linda_G
Kilo Sage

We are using the new Resource Management Workspace, I have a resource plan on a project. The resource plan end date is 2/22/25. I booked time to the project last week but am seeing the following:

- The actuals do not show under the project on the Resource Management Workspace where the blue box is.

- The time DOES show under the timecard related list on the project and it shows as processed.

- The time does not show on the project workspace in the resource assignment view.

 

Screenshot 2025-02-26 at 9.03.16 PM.png

What am I missing?  Any help is appreciated.

1 REPLY 1

mev
Tera Contributor

Hey Linda, did you figure this out? I'm also experiencing this same issue of missing actuals on the resource management workspace.  They show on the resource aggregate reports and allocation workbench though. time cards have been processed as well like you said.  

 

Thanks,

Patrick