Hello,

We've started using Resource Management in our department and at the moment a lot of Allocated Resource Plans have huge amount of mistakes and we are interested how we can fix these resource plans. I've found information that if I want to make changes and use the canceled plan again, I can edit a canceled plan. To move the resource plan back to the Planning state, click Re-plan, but I've never seen the mentioned button.

Could you please clarify how existing Allocated Resource Plans could be fixed, modified, updated.

Thank you.

1 ACCEPTED SOLUTION

User147276
Giga Guru

The Re-Plan UI button only appears on canceled plans, if there are no allocations in the resource allocation related list on the plan.

find_real_file.png

View solution in original post

2 REPLIES 2

User147276
Giga Guru

The Re-Plan UI button only appears on canceled plans, if there are no allocations in the resource allocation related list on the plan.

find_real_file.png

Hello, thank you for help!

During additional testing it has been discovered that only Resource Plans for future periods could be Re-planned. For example in case Resource Plan has been created for the period starting from tomorrow till the project end date it is possible to Re-plan it even it has been previously Allocated, but if start date of Resource Plan is in the past there is no chance to Cancel and Re-plan Resource Plan even if the previous state of the Resource Plan was Planning.