In Resource and capacity management, How to set the capacity of the resource to ZERO if the resource is going on Maternity leave?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
Hi @Bhavya19
Agent assignment depends on the technician's availability. In ServiceNow, the technician's Work Schedule/Calendar can be configured to define their working hours, availability, and planned time off.
For example, if a technician is going on maternity leave for a specific period, that time can be marked as Time Off/Unavailable in their schedule. During that period, the technician will not be considered for work assignment or scheduling.
can you please refer the below article for the more reference
https://www.servicenow.com/community/fsm-articles/building-agent-work-schedules-and-providing-data-v...
If my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.
Thank You
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago - last edited 3 weeks ago
Hi @Bhavya19
Please refer the below screenshots.
In the Schedule Entries, there is a Type field. You can select Time Off from there.
If you found my response helpful and it answered your question, please consider marking it as the accepted solution and giving it a thumbs up. It helps others in the community find the solution more easily.
Thank you!
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago - last edited 3 weeks ago
Hi @Bhavya19
I hope you are doing great!
Just for your information, the above configurations are related to FSM Capacity Management.
and for the SPM resource and capacity management then you can refer this below article i hope this will work for you
https://www.servicenow.com/community/spm-articles/resource-assignment-and-capacity-planning-guide/ta...
Thank you!