Resource Assignment in Project workspace

ashwinipingle
Tera Guru

Dear SPM experts,

We have a Vancouver instance - glide-vancouver-07-06-2023__patch5-12-01-2023.

We have enabled the Resource Assignment in Project Workspace feature. 

Project workspace is 4.2.0. The property sn_pw.enable_resource_planning is true.

I can see the toggle button for Resource Plan and accordingly get a Resource Assignment view in the bottom part of screen with a Add Resource button. However I am unable to see the Resource Assignee for each task in the plan.

What else is missed out besides above settings?

Best Regards,

Ashwini Pingle

Edit - Resource Allocation is not getting created at all from the project workspace thru the Res.Assignment screen/panel.

1 REPLY 1

Yuqi
Tera Contributor

Hi ashwinipingle,

 

I had the same problem, and activating capacity planning attributes (group, skill, role) has solved the issue.

BTW, did you figure out how to sync the creation of resource assignment in the backend from the project workspace?

 

Best regards,

Yuqi