Hi everyone,
I am currently working with SPM Standard and using Resource Plans. I wanted to clarify whether Resource Assignments can be used in this setup or if they require additional plugins/licensing.
From my understanding, Resource Assignments are part of Resource Management capabilities, but I am not sure:
- Which exact plugins are required (e.g., Resource Management –
com.snc.resource_management) - Whether they are supported in SPM Standard or only in SPM Professional/Advanced
- If activating the plugin alone is sufficient or licensing is mandatory (Paid/Unpaid)
1 REPLY 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
- Which exact plugins are required (e.g., Resource Management –
com.snc.resource_management) - (Answer: you need the Project Workspace (sn_pw) plugin and the Resource Management Workspace (sn_resource_mgmt_ws) plugin. Refer: https://www.servicenow.com/community/spm-articles/resource-assignment-guidance-how-to-enable-and-sta....)
- Whether they are supported in SPM Standard or only in SPM Professional/Advanced (yes)
- If activating the plugin alone is sufficient or licensing is mandatory (Paid/Unpaid) (Answer: these are paid one, Better you check with your Servicenow representative once on this)