Resource Assignment Vs Resource Plans

hurbanus
Tera Contributor

Can you use both Resource Plans and Resource Assignments in Zurich?  Is there any negative impacts if they are both being used?

1 REPLY 1

Tanushree Maiti
Tera Patron

Hi @hurbanus 

 

Using both classic Resource Plans and the newer Resource Assignments in the Zurich release is not recommended.

"As an end user, when you are using resource assignments, you can ignore the resource plans and so you do not have to manually update anything in the resource plans. "

Refer: https://www.servicenow.com/community/spm-forum/resource-assignment-and-resource-plan-completion/m-p/...

https://www.servicenow.com/community/spm-forum/resource-assignment-or-resource-plan/m-p/3223712/emcs...

 

 

Please Accept the solution if it assisted you with your question & Mark this response as Helpful.
Regards
Tanushree Maiti
ServiceNow Technical Architect
LinkedIn: https://www.linkedin.com/in/tanushreemaiti