Resource Capacity

Reena Kumari2
Tera Contributor

Hi team,

Can we change the resource capacity from FTE to hours at Strategic Planning Workspace.

Please see the screenshot below, in the image below, we can see it's displaying number of person(FTE), I want it in hours instead of FTE:-

ReenaKumari2_0-1758884390622.png

 

@Namita Mishra 

Thanks,

Reena Kumari

1 REPLY 1

M Iftikhar
Mega Sage

Hi @Reena Kumari2,

In Strategic Planning Workspace the capacity is shown in FTE by design. The system calculates hours from resource schedules, but there isn’t an out-of-the-box option to switch the display to hours. If you need hours, the usual approach is to build a custom report/dashboard or explore a UI customization. Otherwise, this would be a good candidate for a feature request with ServiceNow.

Thanks & Regards,  
Muhammad Iftikhar  

If my response helped, please mark it as the accepted solution so others can benefit as well.