Resource Data Visualization - Trying to trend by when the work is actually planned to happen

ben244536969617
Tera Contributor

Hi All

 

I am trying to create a visualisation of Resource Assignments (RAs) that breaks down 'Unassigned' RAs by Role and Month. Seems easy enough. However what I can't figure out is how to find where the RA is broken down across the months.

 

If I go to the Resource Management Workspace and choose the 'Unassigned Assignment Requests' view, I can see at the bottom a list of unassigned tasks with start & end dates and then a calendar of how many Person Days are allocated to each for each month

 

RoleTaskStartEndTask EffortJanFebMaretc
Business AnalystDemand 0101/01/2628/02/261055  
ArchitectDemand 0101/02/2631/05/2640 101010
Business AnalystDemand 0201/02/2630/05/2630 7.57.57.5

 

What I can't seem to do is get at those values on the right hand part of the table. What I would like to be able to do is create the below (which takes the total number of days requested for each role by month - so Business Analyst 5 days for Demand 01 + 7.5 for Demand 02 = 12.5 days):

 

RoleJanFebMaretc
Business Analyst512.5  
Architect 101010

 

And then produce a stacked column chart that shows this data like this (which is what I have managed to get to):

ben244536969617_0-1765876834962.png

But trended by the total aggregated effort in each month (not by start date as it is in that example)

Can anyone help me? Clearly the data exists somewhere, but I can't figure out where.

 

UPDATE: 

I have been playing around with the Attribute Aggregate Monthly Effort table, but this only seems to contain items that have been Approved or Assigned to an actual Employee? 

Thanks

 

Ben

 