Resource Plan migration of customized allocation instead of even allocation
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-22-2025 05:51 AM
Dear Community,
I need to migrate Resource Plans to Resource Assignments. Based on the documentation, the Allocation spread is always Even. Our Resource Plans has some customisations for monthly values, like 3 FTE for January, 6 FTE for February, then 3 FTE for March again. The migration script works as mentioned, like after the migration, all month will have 4 FTEs (evenly spread) in the Resource Allocation. We need to keep the original monthly values. Does anybody else experienced this issue, what was the solution?
Thank you!
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-22-2025 06:25 AM
Hi Gergely,
If you have created a resource plan on a group and with the spread mentioned above(3 FTE for January, 6 FTE for February, then 3 FTE for March), it will evenly spread the effort evenly across the 3 months for all the members of the group. So, what you mentioned is correct and each month will have 4 FTEs.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-22-2025 07:11 AM
Exactly, our problem is that several thousands of resource plans are affected, so we will lose data. Can you suggest any solution for this issue?